You can finally see the shape of things to come, back tomorrow from 0830 till 1600 hours.
Toilet in place, now just boxwork, and tiling.
Floor plate fixed down and marked, as well as the wall end plate.
All the floor plates to the workshop have been fixed down and the door entrance shown, we can strt to see the areas available now.
The timber is stacked ready for various jobs
End stud wall going up with the storage area timber joists above.
The internal size of the Workshop can now be seen clearly, with all the Workshop studs, doorliner, up and ready waiting to be plasterboarded.
Closer view of the Workshop with the ceiling joists going in, leaving a loft hatch for storage.
Here you can see the doorway into the workshop and joists above to 12′ x 4′ games table position.
Ceiling joists on the noggins waiting to be lifted up into position.